Recently Phase I of CEIEC Ruidesheng Production and Research Center Project completed its structure construction work in advance. CEEDI undertakes the project design and management. Mr. An Zhixing, Vice President of CEEDI participated in the completion ceremony.
This project is located in Beijing Economic and Technological Development Zone and the total floor area of the center is 165000m2. The construction work started on 1st January 2015, and planned to complete on 30th June 2016. Due to the completion in advance, the client highly recognized CEEDI’s contribution to the project due to the efficiency and quality of the construction management.